Plumbing & Construction Update
/Patients, Staff & Community,
The plumbing project in the hallway in front of IT and down to the materials manager's office (the boardwalk) is beginning to wind down. The corner restrooms will be shut down until Wednesday of next week, possibly for the entire coming week to finish the underground wastewater lines.
Once the wastewater lines are completed, it is a matter of backfill, concrete, and vinyl plank flooring. This is on schedule to be completed by the end of the month, possibly sooner.
The remodeled restrooms by materials management and employee entrance had flooring completed yesterday and plans are on schedule to be complete and ready for use in 2 weeks. This is dependent on the ability to get the final approval from inspectors.
It has been a long road for these two projects but it will be well worth it. Thank you to all for your patience during these projects.